Swift/Deploy Plan - R720xds in tampa

From Wikitech
< Swift(Difference between revisions)
Jump to: navigation, search
(Proposed schedule: forgot to mark as done when I updated the date)
(Proposed schedule)
Line 48: Line 48:
 
:add weight to ms-be5 at 100
 
:add weight to ms-be5 at 100
  
* Fri Feb 1
+
* Thur Feb 7 - done
 
:remove weight from ms-be12 to 33
 
:remove weight from ms-be12 to 33
 
:put in new ms-be11 at 33
 
:put in new ms-be11 at 33

Revision as of 18:22, 7 February 2013

Draft, edit at will

Current status

  • Currently replaced: ms-be6,7,8,10
  • Host which has fallen over a few times recently: ms-be3
  • Hosts with disk issues (so they should be replaced next): ms-be5,11,12
  • Other hosts with ssds: ms-be9
  • The rest: ms-be1,2,4

Proposed schedule

Bah, the last proposed schedule died a horrible death; it was taking 5 days for one complete run of the object replicators. After some back of the napkin calculations, here's a new schedule (old one is hidden in html comments). I'll be monitoring to see if the object replication runs actually finish in two days (nope. 3.5 days) when we move this much data around; if they do, we'll try the below:

  • Mon Dec 10 -- done
take out the two bad rings (remove, not weight 0):
d321 ms-be10 (10.0.6.209) sdc,
d294 ms-be7 (10.0.6.206) sda (which was replaced but we can't get linux to see it so whatever)
add weight to ms-be8 (10.0.6.207) to 100
add weight to ms-be10 (10.0.6.209) to 100
  • Fri Dec 14 -- done
remove weight from ms-be5 (10.0.6.204) to 66
add weight to ms-be7 (10.0.6.206) to 100
  • Fri Dec 21 -- done
remove weight from ms-be5 to 33
put in new ms-be3 to 33
  • Mon Dec 31 -- done
remove weight from ms-be5 to 0
add weight to ms-be3 to 66
  • Tue Jan 8 - done
power off ms-be5
remove weight from ms-be11 to 66
put in new ms-be5 at 33
  • Mon Jan 13 - done
remove weight from ms-be11 to 33
add weight to ms-be3 to 100
  • Mon Jan 21 - done
remove weight from ms-be11 to 0
add weight to ms-be5 at 66
  • Mon Jan 28 - done
remove weight from ms-be12 to 66
power off ms-be11
add weight to ms-be5 at 100
  • Thur Feb 7 - done
remove weight from ms-be12 to 33
put in new ms-be11 at 33
  • Mon Jan 7 - from here on dates need to be recalculated
remove weight from ms-be12 to 0
add weight to ms-be11 at 66
  • Wed Jan 9
remove weight from me-be9 to 66
power off ms-be12
add weight to ms-be11 at 100
  • Fri Jan 11
remove weight from ms-be9 to 33
put in new ms-be12 to 33
  • Mon Jan 7 -- dates from here on need t be recalculated
remove weight from ms-be9 to 0
add weight to ms-be12 to 66
  • Wed Jan 9
remove weight from ms-be2 to 66
power off ms-be9
add weight to ms-be12 to 100

Note: ms-be9,1,2,4 go to ceph testing

  • Fri Jan 11
remove weight from ms-be2 to 33
  • Mon Jan 14
remove weight from ms-be2 to 0
  • Wed Jan 16
remove weight from ms-be1 to 66
power off ms-be2
  • Fri Jan 18
remove weight from ms-be1 to 33
  • Mon Jan 21
remove weight from ms-be1 to 0
  • Wed Jan 23
remove weight from ms-be4 to 66
power off ms-be1
  • Fri Jan 25
remove weight from ms-be4 to 33
  • Mon Jan 28
remove weight from ms-be4 to 0
  • Web Jan 31
power off ms-be4


This schedule will be adjusted (shorter or longer) as we see how the cluster behaves.

Note: all hosts get ssds

Logistics

  • What is our deadline for returning the C2100s?
  • Do we have enough ssds to put in all remaining 720xds? If not let's get them (and what's the turnaround time for those?) YES we do.