Eqiad Migration Planning
From Wikitech
Contents |
Coordination
- We now have an incomplete tracking ticket in RT that depends on more specific tickets.
- Sept 12 Update - http://etherpad.wikimedia.org/TechOps-12Sept2012
Needed Server Builds
- App and API Apaches
- Image scalers? (completed Precise build and deployed at Tampa). Ready to deploy @ Eqiad
- Apache - completed, and being deployed in both Tampa (in production) and Eqiad (for testing)
- JobRunners
- will be on separate boxes in eqiad
- Peter will set up separate (i.e. non-appserver) job runners in Tampa first, as part of the precise upgrades - completed
- set up the same in eqiad
- we'll raise the fork limit from 5 to something like 12
- Swift
- servers online; needs cluster replication enabled - netapp replicatio enabled
- Still need to migrate Math, Captcha, Misc objects from ms7 to Swift
- H/w issues need to be resolved - H/w being installed and final batch to ship on 5th Dec
- Might have to run Swift and ImageScalers in Tampa while the rest of the stack are running in Eqiad
- Aaron to test performance lag
- Memcached servers
- mc01 - mc16 (Tampa) in production - done
- mc1001-mc1016 OS installed, ready for puppet to be run.
- Networked but issues with the Intel 10gNics and Dell's SPF+ - workaround available; getting new SPF+
- Decided to use Redis and use MW multi-write feature to write to both existing MC and the new MC servers, then enable Redis replication from Tampa to Eqiad
- Databases - done
-
one more slave is needed per shard
-
- Poolcounter
- Done: helium and potassium are installed and puppetized
- Netapp
- /home/wikipedia for deployments
- /home - completed in Tampa, not strictly necessary in eqiad
- Deployment server (fenari's deployment support infrastructure part, misc::deployment etc)
- awaiting new misc server racking next week
- Hume equivalent (misc::maintenance) - postponed
- Application logging server - for mediawiki wmerrors + apache syslog
-
eqiad version of the udp2log instance on nfs1 that writes to /home/w/logs - Done: server 'flourine' for apache logs
-
- Upload Varnish - done
- Deployment Host (10 minutes job according to Tim, and he volunteered to own it)
-
Server OS install - Deploy from deployment host to all application servers
- rsync the deployment code from the primary deployment server to the secondary
- Require a clean git repo
- Application servers in the other datacenter will use the secondary deployment system for rsync
-
Software / Config Requirements
- Varnish software to handle media streaming efficiently
- awaiting patch from Varnish Software (target Sept?)
- patch MediaWiki to use a different upload hostname for large files. Then we could use Squid or some specialized media streaming proxy for large files.
- MediaWiki deploy support for per colo config variances [Bugzilla 39082]
- generating eqiad and pmtpa dsh groups
- new mediawiki conf files for eqiad
- replicating the git checkouts, etc. to new /home
Actually Failing Over
- deploy db.php with all shards set to read-only in both pmtpa and eqiad
- deploy squid and mobile + bits varnish configs pointing to eqiad apaches
- master swap every core db and writable es shard to eqiad
- deploy db.php in eqiad removing the read-only flag, leave it read-only in pmtpa
- the above master-swap + db.php deploys can be done shard by shard to limit the time certain projects are read-only
- dns changes - our current steady state is to point wikipedia-lb.wikimedia.org in the US to eqiad but future scenarios may include external dns switches.
- Swift replication reversal - from Eqiad to Tampa
Improving Failover
- pre-generate squid + varnish configs for different primary datacenter roles
- implement MHA to better automate the mysql master failovers
- migrate session storage to redis, with redundant replicas across colos
See more
- Records and original tracking doc - http://etherpad.wikimedia.org/EQIAD-rollout-sequence
- Category:Eqiad cluster
Parking Lot Issues
- Identify and plan around the deployment/migration date -
tentatively Oct 15, 2012[see below]. Need to communicate date.- Migration needs to happen before Fundraising season starts in Nov.
- Vacation 'freeze'; all hands on deck week before and after deployment
- Why? Not every person is vital to migration.
- migrate ns1 from tampa to ashburn, but not a critical item.
- An update from CT Woo from October 2012 regarding the status of the migration is available here. It looks like it'll be pushed back to January or February 2013 (post-annual fundraiser).